Herring Bridge, Great Yarmouth
A vital third river crossing: open for business
Great Yarmouth in Norfolk has been home to many industries – from fishing, to tourism, oil and gas and, most recently, renewables and offshore wind.
But the port’s location on a long spit of land, bounded on one side by the River Yare and on the other by the North Sea, has long created issues for traffic wanting to get across the river quickly.
As a result, Norfolk County Council made the construction of a third town-centre river crossing one of its key priorities: recognising its potential to help attract investment to the area, create jobs and give local people a better quality of life.
In 2019, the Council awarded BAM Farrens Joint Venture (BFJV) the contract for the design, construction and initial operation of the innovative new bridge and its surrounding infrastructure.
The dual carriageway 68 metre twin-leaf bascule bridge is designed to open in the middle up to 28 times a day, to allow taller river traffic through. Access roads, a new roundabout, underpasses, quay wall refurbishments, drainage and flood attenuation works are all supported by extensive landscaping.
The Herring Bridge – named for the town’s historic association with the fishing industry – opened in 2024 and has improved links through the area, transformed travel across the town and delivered a lasting social and economic legacy.
Project details
- Client
Norfolk County Council - Principal contractor
BAM Farrans Joint Venture (BFJV) - Lead designer
Roughan & O’Donovan (ROD) - Bridge designer
H&H - MEICA/designer and supplier
Qualter Hall - Structural steel fabricator
Victor Buyck - Total project value
£121 million
Tonnes of concrete in each bridge counterbalance
Spent on local supply chain and materials (within 30 miles)
Equal to the weight of the new bridge
Tolerance when positioning bridge leaves
The challenge: managing a complex, waterside site next to a busy working port
The town-centre site for the new crossing brought with it a unique set of challenges, not least the difficult ground conditions in the area: consisting of soft and instable layers of sand and peat.
Marine works also needed to be carried out in the live port environment, with minimal opportunities to close the river to traffic. On the other side of the river, construction took place right next to a residential area. That meant working very closely with local stakeholders was a priority, even before work started.
The bridge structure itself involved complex mechanical, electrical, instrumentation, control and automation (MEICA) challenges. It needed to be as light as possible, but also energy efficient, easy and quick to open and close reliably in just 90 seconds, many times a day.
Much of the work on the project was carried out through 2020 and 2021, during the height of the Covid pandemic, adding yet another layer of complexity.
The BFJV solution: building in certainty and quality
When it came to preparing the site, a huge and complex piling operation was needed to take the weight of all the access roads and surrounding infrastructure. This involved installing an interlinked network of pre-cast concrete piles, to support the structures and prevent any future settlement.
Thousands of tonnes of sand and soil were recycled from a nearby WW1 runway, to use as fill across the project.
A small but important part of the preparation work involved relocating and creating new habitations for a colony of water voles found around the site: supporting regional efforts to reverse the decline in population.
Building a bascule bridge of this scale on site would have involved months of disruption to local road and river traffic, not to mention significant technical, quality assurance, and health and safety challenges.
After weighing up the options, the decision was taken to fabricate the two giant steel leaves for the bridge offsite. The specialist contractor in Belgium constructed the two giant steel leaves for the bascule, each weighing 770 tonnes and measuring 45m by 24m.
The first leaf was loaded onto a delivery barge and brought across the North Sea in early 2023, followed rapidly by the second. BFJV successfully installed both leaves during a single 72-hour river possession in March 2023, using a vast floating crane.
Early engagement and close collaboration between BFJV, the client, key contractors and the supply chain was essential to the success of the project.
The results: collaboration delivers a lasting legacy
The Herring Bridge has had a major impact on congestion in the town, delivering environmental, social and economic benefits.
Throughout the project an extensive campaign of stakeholder engagement helped minimise disruption to residents and businesses.
Many small and medium sized enterprises in and around the town were involved in the project, which provided numerous employment and work experience opportunities. Close links between BFJV, Norfolk County Council and local schools and colleges helped to ensure that the project delivered a lasting legacy in terms of skills and expertise.
The project returned 30% social and local economic value (SLEV).
BFJV is currently responsible for operating the bridge 24/7, as well as on-going maintenance works. Several local team members recruited for the construction phase transferred to operational roles once the bridge was complete.
In Summer 2024, the bridge was named Major Project of the Year at the New Civil Engineer awards. The project also won Major Project of the Year at the 2024 Highway Awards and received the overall Highways Special Merit award.
“We are already seeing how the bridge is transforming travel around the town and to see it recognised with multiple national awards is fantastic recognition for all of the team who have worked tirelessly to make it happen.”
Councillor Graham Plant Former Cabinet Member for Highways, Infrastructure and Transport, Norfolk County Council